Δευτέρα 4 Απριλίου 2016

Construction of a small-scale biodiesel plant

The process for making biodiesel consists of the following steps:

·         Preheat used vegetable oil to remove water

·         Determine oil pH and measure appropriate quantity of NaOH and methanol

·         Mix reactants

·         Allow glycerin to settle out, drain glycerin and send to methanol recapture


·         Wash biodiesel to remove trace contaminants

·         Set in the sun to drive off traces of water


The process design is divided into the following stages:

  1. pre-heat,
  1. processing,
  1. wash,
  1. methanol recapture,
  1. water treatment
  1. solar heat.



Preheat Stage

The role of the preheat stage s to remove any water that might be mixed with the used vegetable oil. Water is detrimental to the transesterification process and must be removed as much as possible. Heating the oil to 50-54 oC is enough to cause the water to settle out.


There are two preheat tanks. The tank volumes are 150 gal each. Using two tanks allows for the continual receiving of used vegetable oil. Hot water flows from a propane heater and through a heating coil to heat the oil, the cooled water is then returned to the heater.


The valve system is designed such that hot water will flow through only one tank at a time, likewise the vegetable oil will be pumped out of the tanks sequentially. While one tank is pre-heating, the other is available for receiving used oil.

 


 Figure 1 - Schematic of Preheat Stage

  
Processing Stage

The processing stage consists of two reactor tanks, each connected to its own pump for recirculating and mixing of the reactants. The first tank, reactor A, is tall and narrow with a conical bottom. This reactor shape provides adequate mixing of the fluid when recirculated by the pump. The second tank, reactor B, is bulkier and rounded on the bottom, which would create dead zones if mixed by simple recirculation. To overcome this problem and ensure adequate mixing in both processing tanks, a mechanical mixer with impellers was purchased. Static mixers were also purchased to increase mixing within the pipes.


The goal of the processing piping system is to ensure flexibility of the system while maximizing use of only two pumps. The primary feature of this system is that it allows for the transfer between the two reactors. Used vegetable oil can be pumped into either tank via pump A, and then recirculated with the reactor tanks via their respective pumps. Contents can be transferred between the two tanks via this piping scheme. The proposed processing method is outlined as follows:


·         Used vegetable oil is pumped from the preheat stage into reactor B.
·         Mixed methoxide is added to reactor B and circulated to provide initial mixing.

·         Half of the mixture is then transferred to reactor A, and both tanks are recirculated for the
        required reaction times.

·         Following the reaction, the tanks are allowed to settle and glycerin is drained out for       eventual methanol recapture.
·         The biodiesel product is pumped out towards the washing stage.


Initially mixing all of the reactants in one container ensures homogeneity of the oil:methoxide ration within both reactors. This removes one measuring step. Using both reactors for processing allows for eventual expansion. The system also maximizes the use of the two pumps, which perform all the required transferring and recirculating.


Pump A is significantly larger than pump B. It also has more power and the additional feature that it can run dry without damaging. These two features make pump A the best choice for pumping used vegetable oil into the reactor, as it doesn’t require the operator to monitor the level in the preheat tanks.



 



  
 Figure 2 - Schematic of Processing Stage

  
Washing Stage

There are many methods of washing available when processing biodiesel. An ideal washing method maximizes interaction between the fresh biodiesel and washing water, while minimizing the risk of emulsifying. Alternatively, water and biodiesel could be simply mixed  manually. This works well for small batches, however the manual aspect makes it increasingly time-consuming with increase in batch size, and more difficult to control to avoid emulsification if automated.


The most commonly recommended method of washing biodiesel is aeration, whereby air is bubbled through layers of water and biodiesel. The bubbles rising into the biodiesel carry with them a thin film of water. The biodiesel contaminants dissolve in the water. When the bubble bursts, this water falls out of the biodiesel layer and returns to the water layer, brining the contaminants with it. This method yields a very high water-biodiesel surface area and minimizes the risk of emulsification. It also has a lower water requirement.


The wash tank design makes use of the following items:

·         A 1 m3 plastic tank donated by a paint company.

·         The compressor required for the operation of the pneumatic pumps.

·         Lengths of ½” PVC piping for the aerator.



The aerator is constructed by drilling small holes along the PVC pipe at 3” intervals. Four lengths of tubing, running parallel along the bottom of the tank, are connected to a single shaft extending to the top of the tank. The compressor connects to a regulator and then to the shaft. The rate of air flow through the aerator, and thus the rate of bubbles, is controlled by the regulator.


For each batch, an amount of water equal to half the volume of biodiesel is added to the wash tank, followed by the biodiesel. The product is bubble-washed for 6 hours and then let to settle for 1 hour. This wash is repeated three times, each time the water is drained from the bottom and new water is added.


One identified problem with the aerator system is that biodiesel degrades PVC glue over time. As such, it is important to minimize the interaction between the aerator and the biodiesel. The paint tank has a built-in drain located at the bottom, but an additional tap was installed a few inches higher, which is the tap that will be used to drain the water to ensure that a certain volume of water will remain above the aerator at all times, protecting the PVC piping.


The total volume of the wash tank is 350 gal. Given that some airspace is required at the top, and

1/3 of the tank ΄s volume must be water, this wash tank cannot wash biodiesel batches greater than 200 gal. Should we choose to increase production, a second wash system would be required.


 Figure 3 - Schematic of Wash Tank

  



Methanol Recapture

Methanol is the most expensive input for the biodiesel process. The price is tied to the price of oil, and as such is at risk of instability as crude prices rise.


In order to ensure that the reaction consumes all of the vegetable oil, methanol is added in excess to force the equilibrium to the right. This excess methanol ends up in the glycerin by-product and represents a significant loss. Methanol in the glycerin also limits the potential for marketing it as a product, as the combination is deemed unsafe and flammable.


Given the relatively low boiling point of methanol, it is possible to recapture the methanol via a simple still. The mix of glycerin and methanol, still liquid following the reaction stage, can be heated to vaporize the methanol. These vapors can then be condensed and recycled, maximizing use, reducing waste, and lowering overall processing cost.


An additional methanol recapture system is needed and this could  be constructed of items that can be found easily.






 Figure 4 - Schematic of Methanol                                   Figure 5 - Photograph of a Methanol

Recapture Unit                                                                Recapture Unit




The glycerin by-product is poured in to a chemical container through a funnel in the lid. The container must be sturdy and air-tight. An electric heater heats the glycerin to the methanol boiling point of 66°F. The vapors rise through the bucket and into a length of copper tubing. The copper tubing then coils as it enters a condenser. Cold tap water passes through the condenser, cooling the methanol vapors to a liquid. The liquid falls through the copper tubing where it is collected at the bottom. Once the liquid methanol stops flowing, the process is complete and the glycerin is drained from a tap while still liquid.






Water Treatment

In an effort to reduce the overall impact of biodiesel production, water consumption and recycling were considered. Three wash stages are required for biodiesel production, the first stage taking out the most contaminants and each subsequent wash containing significantly less. Water recycling then becomes an ideal method for reducing overall water consumption within the process.


Each wash stage, at maximum production capacity uses 100 gal of water. The first wash produces water too dirty for reuse, but the water from the second and third washes are fairly clean. To reuse the water, two interim storage tanks of 100 gallons each will be placed near the washing station.

The water from the second and third washing stages will be pumped into the storage tanks and then reused in the following wash process. The general recycling process is outlined  Figure 6. The water from wash 3 will be reused for wash 2, and the water from wash 2 reused in wash 1. Once the loop is established, the required water consumption for washing will be reduced by 2/3, requiring only half a gallon of water per gallon of biodiesel instead of 1.5.










Figure 6 - Outline of Water Recycling Process



In addition to water recycling, the following water treatment options is also explored, with the hopes of bringing the process water demand to nearly zero.



  
Solar Distillation

This method of water purification produces almost perfect distilled water and would remove all of the glycerin, methanol, and dissolved solids. Solar distillation, however, is highly inefficient and would require an extremely large surface area in order to treat the amount of water needed for biodiesel production. Through some research and testing, it was determined that a solar still covering an area of 4m2 could only treat about 30 gallons a week, simply not enough and anything larger would take up too much space and be too costly to implement.


Slow Sand Filtration

Slow sand filters are very efficient at removing organic solids and quite inexpensive to construct. The problems with this type of system are that it may clog up if the waste water is too turbid, and it will not remove dissolved solids. This means that the waste water from the washing stage of biodiesel production might have to be pre-treated to decrease turbidity in order to pass it through a sand filter. Furthermore, it remains unclear exactly how much dissolved caustic soda would remain in the treated water and its effects on whether the water would be acceptable for re-use. Finally, there may be a problem with using a slow sand filter since most of the actual water treatment is performed by the microorganisms living in the top layer of the sand and it is still unclear how these organisms would fair with the filter not in constant use..

  
Methanol Evaporation

In some of the literature examined for the biodiesel internship there was mention of heating the unwashed biodiesel to boil off the methanol and cause the suspended solids to precipitate out. The theory is that methanol evaporates at a much lower temperature than biodiesel (only 60C) and thus could safely be evaporated out which would release the suspended solids leaving clean, useable biodiesel. This step would, in theory, altogether eliminate the need for a wash stage and thus eliminate the need for clean water..


Solar Heating

In further attempts to reduce the environmental impact of biodiesel production, solar heating could be investigated. The energy requirements for the oil pretreatment stage could easily be met using a solar heating system.


The design requires a pump to allow the working fluid to circulate through the element up towards the solar panel. A debate emerged between two possible options: indirect or direct solar heating. Direct heating involves having the used vegetable heat directly as it flows through the coil of the solar panel. However, this option is eliminated as it causes tube-side fouling hence resulting in higher maintenance needs.






Δεν υπάρχουν σχόλια:

Δημοσίευση σχολίου